Civil Engineering MCQs

Instruments Questions with solutions MCQs

1. Match the list-1 with list-2 and select the correct answer using the codes given below.

List-1 (Name of the instrument):    List-2 (Purpose): 

a. Current meter,    1. Control silt entry into the canal, 

b. Echo sounder,    2. Control water levels and flow rates in canal, 

c. Head regulator,    3. Depth of flow, 

d. Sluice gate     4. Velocity of flow of water


A

1 2 4 3

B

1 3 2 4

C

4 3 1 2

D

1234

Instruments J.E Civil 2023
Correct Answer : C
Explanation :

a-Current meter → velocity (4), b-Echo sounder → depth (3), c-Head regulator → silt control (1), d-Sluice gate → control flow (2). Correct sequence is 4 3 1 2.