1. Consider the following surveys

(i) Reconnaissance survey

(ii) Preliminary survey

(iii) Traffic survey

(iv) Location survey.

The correct sequence of surveys conducted to finalize the railway alignment is


A

(i) (iii) (ii) (iv)

B

(i) (iii) (iv) (ii)

C

(iii) (i) (iv) (ii)

D

(iii) (i) (ii) (iv)

Surveys for Railway Alignment J.E Civil 2023
Correct Answer : A
Explanation :

The sequence is reconnaissance → traffic → preliminary → location survey to finalize alignment.